Riders · School for the Blind and Visually Impaired · Article III: Agencies of Education

Capital Budget

Rider 2 in the 2026-27 Act, page III-44

Through the session

  1. 2024-25 Act In current law rider 2
  2. Introduced (Senate) Amended rider 2
  3. Introduced (House) Amended rider 2
  4. Senate substitute Amended rider 2
  5. House substitute Amended rider 2
  6. House passed Unchanged rider 2
  7. Conference Amended rider 2
  8. 2026-27 Act Unchanged rider 2

Pick any two steps to compare their wording.

What changed in the text

House passed → Conference: 6 passages changed.

Capital Budget. None of the funds appropriated above may be expended for capital budget items except as listed below. The amounts shown below shall be expended only for the purposes shown and are not available for expenditure for other purposes. 2026 2027 a. Acquisition of Information Resource Technologies (1) Administrative & Infrastructure Upgrades $ 28,000 $ 28,000 (2) Instructional Materials and Technology 280,000 280,000 Total, Acquisition of Information Resource Technologies $ 308,000 $ 308,000 b. Acquisition of Capital Equipment and Items (1) Furniture Replacement & Project Completion $ 1,066,000 $ 0 (2) Campus Security Upgrades 600,000 0 Total, Acquisition of Capital Equipment and Items $ 1,666,000 600,000 $ 0 Total, Capital Budget $ 1,974,000 908,000 $ 308,000 Method of Financing (Capital Budget): General Revenue Fund $ 1,974,000 908,000 $ 308,000 Total, Method of Financing $ 1,974,000 908,000 $ 308,000

Removed words are struck through; added words are underlined. Sources: House passed · Conference.

Every version: numbers, statuses and source pages
VersionRider Against the version beforeAgainst the current budget Source
2024-25 ActGeneral Appropriations Act, 2024-25 Biennium 2 First version — Page III-37
Introduced (Senate)Senate Bill 1 as introduced (LBB recommended, Senate) 2 Amended — Page III-46
Introduced (House)House Bill 1 as introduced (LBB recommended, House) 2 Amended — Page III-44
Senate substituteCommittee Substitute for Senate Bill 1 2 Amended Amended Page III-40
House substituteHouse Committee Substitute for Senate Bill 1 2 Amended Amended Page III-39
House passedSenate Bill 1 as passed the second house 2 Unchanged Amended Page III-38
ConferenceConference Committee Report for Senate Bill 1 2 Amended Amended Page III-41
2026-27 ActGeneral Appropriations Act, 2026-27 Biennium 2 Unchanged Amended Page III-44
Full text of each wording

Introduced (Senate), Introduced (House), Conference, 2026-27 Act

Source, page III-44

Capital Budget. None of the funds appropriated above may be expended for capital budget items except as listed below. The amounts shown below shall be expended only for the purposes shown and are not available for expenditure for other purposes.

                                                                 2026              2027

a. Acquisition of Information Resource Technologies

(1) Administrative & Infrastructure

             Upgrades                                       $         28,000  $           28,000
        (2)  Instructional Materials and Technology                  280,000           280,000

Total, Acquisition of Information Resource

        Technologies                                        $        308,000  $        308,000

b. Acquisition of Capital Equipment and Items

        (1)  Campus Security Upgrades                       $        600,000  $               0
        Total, Capital Budget                               $        908,000  $        308,000

Method of Financing (Capital Budget):

     General Revenue Fund                                   $        908,000  $        308,000
        Total, Method of Financing                          $        908,000  $        308,000

House substitute, House passed

Source, page III-38

Capital Budget. None of the funds appropriated above may be expended for capital budget items except as listed below. The amounts shown below shall be expended only for the purposes shown and are not available for expenditure for other purposes.

                                                                       2026                2027

a. Acquisition of Information Resource Technologies

(1) Administrative & Infrastructure

               Upgrades                                           $         28,000    $         28,000
        (2)    Instructional Materials and Technology                      280,000             280,000

Total, Acquisition of Information Resource

        Technologies                                              $        308,000    $        308,000

b. Acquisition of Capital Equipment and Items

(1) Furniture Replacement & Project

               Completion                                         $      1,066,000    $             0
        (2)    Campus Security Upgrades                                    600,000                  0

Total, Acquisition of Capital Equipment and

        Items                                                     $      1,666,000    $             0
        Total, Capital Budget                                     $      1,974,000    $        308,000

Method of Financing (Capital Budget):

     General Revenue Fund                                         $      1,974,000    $        308,000
        Total, Method of Financing                                $      1,974,000    $        308,000

Senate substitute

Source, page III-40

Capital Budget. None of the funds appropriated above may be expended for capital budget items except as listed below. The amounts shown below shall be expended only for the purposes shown and are not available for expenditure for other purposes.

                                                                      2026                2027

a. Acquisition of Information Resource Technologies

(1) Administrative & Infrastructure

               Upgrades                                          $       1,256,000   $        151,000
        (2)    Instructional Materials and Technology                     280,000             280,000

Total, Acquisition of Information Resource

        Technologies                                             $       1,536,000   $        431,000

b. Acquisition of Capital Equipment and Items

        (1)    Campus Security Upgrades                          $        600,000    $             0
        Total, Capital Budget                                    $       2,136,000   $        431,000

Method of Financing (Capital Budget):

     General Revenue Fund                                        $       2,136,000   $        431,000
        Total, Method of Financing                               $       2,136,000   $        431,000

2024-25 Act

Source, page III-37

Capital Budget. None of the funds appropriated above may be expended for capital budget items except as listed below. The amounts shown below shall be expended only for the purposes shown and are not available for expenditure for other purposes.

                                                                        2024               2025

a. Acquisition of Information Resource Technologies

(1) Administrative & Infrastructure

               Upgrades                                            $         28,000   $         28,000
         (2)   Instructional Materials and Technology                       280,000            280,000

Total, Acquisition of Information Resource

          Technologies                                             $        308,000   $        308,000
          Total, Capital Budget                                    $        308,000   $        308,000

Method of Financing (Capital Budget):

     General Revenue Fund                                  $        308,000             $        308,000
          Total, Method of Financing                       $        308,000             $        308,000