Riders · Part 9: Information Resources Provisions · Article IX: General Provisions
Quality Assurance Review of Major Information Resources Projects
Rider 9.02 in the 2026-27 Act, page IX-51
Through the session
- 2024-25 Act In current law rider 9.02
- Introduced (Senate) Unchanged rider 9.02
- Introduced (House) Unchanged rider 9.02
- Senate substitute Unchanged rider 9.02
- House substitute Unchanged rider 9.02
- House passed Unchanged rider 9.02
- Conference Unchanged rider 9.02
- 2026-27 Act Unchanged rider 9.02
Pick any two steps to compare their wording.
What changed in the text
Conference → 2026-27 Act: the same text in both versions.
Removed words are struck through; added words are underlined. Sources: Conference · 2026-27 Act.
Every version: numbers, statuses and source pages
| Version | Rider | Against the version before | Against the current budget | Source |
|---|---|---|---|---|
| 2024-25 ActGeneral Appropriations Act, 2024-25 Biennium | 9.02 | First version | — | Page IX-49 |
| Introduced (Senate)Senate Bill 1 as introduced (LBB recommended, Senate) | 9.02 | Unchanged | — | Page IX-53 |
| Introduced (House)House Bill 1 as introduced (LBB recommended, House) | 9.02 | Unchanged | — | Page IX-53 |
| Senate substituteCommittee Substitute for Senate Bill 1 | 9.02 | Unchanged | Unchanged | Page IX-51 |
| House substituteHouse Committee Substitute for Senate Bill 1 | 9.02 | Unchanged | Unchanged | Page IX-51 |
| House passedSenate Bill 1 as passed the second house | 9.02 | Unchanged | Unchanged | Page IX-51 |
| ConferenceConference Committee Report for Senate Bill 1 | 9.02 | Unchanged | Unchanged | Page IX-51 |
| 2026-27 ActGeneral Appropriations Act, 2026-27 Biennium | 9.02 | Unchanged | Unchanged | Page IX-51 |
Full text of each wording
2024-25 Act, Introduced (Senate), Introduced (House), Senate substitute, House substitute, House passed, Conference, 2026-27 Act
Source, page IX-51Quality Assurance Review of Major Information Resources Projects.
(a) A state agency may not expend appropriated money for a major information resources project unless the project has been reviewed by the Quality Assurance Team (QAT) and approved by the Legislative Budget Board in the agency's biennial operating plan. QAT shall make recommendations based on an analysis of the major information resources project's risk. QAT may request any information necessary to determine a major information resources project's potential risk. QAT may waive the major information resources project review requirements for a project.
(b) (1) QAT may require independent verification and validation services of all major information resources projects projected to result in more than $10 million of overall lifetime expenditures. In addition, QAT may require independent project monitoring, project status reporting, project expenditure reporting, or any additional information necessary to assess a major information resources project's on-going potential for success.
(2) A state agency must notify QAT when the agency advertises a request for proposal, request for bid, or other similar process common to participation in the competitive bidding processes of a major information resources project. The corresponding agency requisition number must be provided at the time of notification.
(3) A state agency must notify QAT within 10 business days when the agency awards a contract for a major information resources project that exceeds $10 million for QAT review.
(4) After a major information resources project has been completed, QAT may also require an agency to submit a project post-implementation evaluation report to determine if the project met its planned objectives.
(5) QAT may take any additional actions or request information as specified in Government Code, Section 2054.1181.
(6) Without regard to the source of monies associated with the expenditures for a major information resources project and without regard to the method of finance of an appropriation associated with a project, QAT may make the requests and impose the requirements or additional actions provided by this section on all major information resources projects regardless of whether undertaken entirely or partially by:
(A) outsourcing or contracting of any sort; or
(B) agency employees.
(c) On request by QAT, the State Auditor's Office shall provide audit and review of:
(1) the major information resources projects;
(2) the information provided by the agencies; and
(3) project management policies and practices.
(d) QAT may request the assistance of the Comptroller regarding the accuracy of major information resources project expenditures and compliance with this Act.
(e) The State Auditor's Office may:
(1) provide an independent evaluation of the post implementation evaluation review process of a major information resources project to ensure the validity of its results; and
(2) send the evaluation to the Legislative Audit Committee.
(f) The Department of Information Resources may issue guidelines for software development, quality assurance, and the review of major information resources projects.
(g) QAT shall require each affected agency to:
(1) quantitatively define the expected outcomes and outputs for each major information resource project at the outset;
(2) monitor cost; and
(3) evaluate the final results to determine whether expectations have been met.
(h) After a major information resources project has been completed, QAT may also require a project demonstration to determine if the project is functioning as intended.