Major Repair and Restoration of Facilities

Priority 4 · one of 16 items in the Department of Criminal Justice's request for 2028-29 · The item begins on page 217 of the request

This is a request, not an appropriation.

What is asked

20282029Two years
All funds$400,898,900$0$400,898,900
Of which general revenue and general revenue-dedicated $400,898,900$0$400,898,900
Positions (full-time equivalents) ——

How it would be financed

Method of financing, as the request prints it20282029
1 General Revenue Fund$400,898,900$0
Total, as the request prints it$400,898,900$0

Where it would land

The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.

Strategy Asked 2028Asked 2029Positions Appropriated 2026Appropriated 2027
03-03-01 Major Repair of FacilitiesIn the current budget: C.3.1 MAJOR REPAIR OF FACILITIES $400,898,900$0— $128,270,000 $0

A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.

After 2029

The agency's estimate203020312032Three years
All funds$762,577,800$767,281,900$1,760,809,500$3,290,669,200
Of which general revenue$762,577,800$767,281,900$1,760,809,500$3,290,669,200

In the agency's words: Continued repair and rehabilitation funding is necessary to maintain our existing physical plant, numbering over 100 correctional facilities statewide. Many of these facilities are over 75 years old. The size, scope and complexity of our physical plant requires substantial ongoing repair and renovation. Identified through condition assessments as well as major work requests prepared by operational staff, the 2028-29 request represents only a portion of the agency's infrastructure repair and rehabilitation needs. We are continuously prioritizing these projects based on security and safety requirements.

The agency's justification

The agency maintains an existing physical plant, numbering over 100 correctional facilities statewide, with many of these facilities over 75 years old. The size, scope and complexity of our physical plant requires substantial ongoing major repair and restoration. Identified through condition assessments as well as major work requests prepared by operational staff, the FY 2028-29 request represents only a portion of the agency’s infrastructure repair and restoration needs . We are continuously prioritizing these projects based on security and safety requirements. This request would fund projects identified in the agency’s FY 2028-29 Capital Expenditure Plan. Projects include: roof repairs, security fencing, fire alarms, lighting, electrical renovations, water/wastewater improvements, and other major infrastructure repairs. Included within this request is funding to increase air-conditioned beds by 15,742 beds in inmate housing areas.

External and internal factors

Funding for this item is critical for TDCJ to meet its statutory (Sec. 493.001(1), Texas Government Code) obligation to confine and supervise adult felons.

As marked in the request