What is asked
| 2028 | 2029 | Two years | |
|---|---|---|---|
| All funds | $611,760,000 | $0 | $611,760,000 |
| Of which general revenue and general revenue-dedicated | $611,760,000 | $0 | $611,760,000 |
| Positions (full-time equivalents) | — | — |
How it would be financed
| Method of financing, as the request prints it | 2028 | 2029 |
|---|---|---|
| 1 General Revenue Fund | $611,760,000 | $0 |
| Total, as the request prints it | $611,760,000 | $0 |
Where it would land
The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.
| Strategy | Asked 2028 | Asked 2029 | Positions | Appropriated 2026 | Appropriated 2027 |
|---|---|---|---|---|---|
| 03-03-01 Major Repair of FacilitiesIn the current budget: C.3.1 MAJOR REPAIR OF FACILITIES | $611,760,000 | $0 | — | $128,270,000 | $0 |
A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.
After 2029
The request marks this item as having no costs after 2029.
The agency's justification
To address increasing populations, the TDCJ is proposing to construct expansion dorms on existing facilities in areas where there is a strong labor pool . A total of 17 dorms would be constructed at 13 locations, increasing capacity by approximately 5,600 beds. It is estimated that these buildings would take 24 months to construct and are estimated to cost $591.8 million in total. This funding request also includes $20 million for the preliminary design of a new prison facility.
External and internal factors
Funding of this program is necessary to accommodate projected population growth.
As marked in the request
- Has an information technology part: No
- Costs anticipated after the two budget years: No
- Involves contracts over $50,000: Yes