Requests · Historical Commission
Eisenhower Birthplace SHS
Priority 19 · one of 21 items in the Historical Commission's request for 2028-29 · The item begins on page 184 of the request
This is a request, not an appropriation.
What is asked
| 2028 | 2029 | Two years | |
|---|---|---|---|
| All funds | $3,500,000 | $0 | $3,500,000 |
| Of which general revenue and general revenue-dedicated | $3,500,000 | $0 | $3,500,000 |
| Positions (full-time equivalents) | — | — |
How it would be financed
| Method of financing, as the request prints it | 2028 | 2029 |
|---|---|---|
| 1 General Revenue Fund | $3,500,000 | $0 |
| Total, as the request prints it | $3,500,000 | $0 |
Where it would land
The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.
| Strategy | Asked 2028 | Asked 2029 | Positions | Appropriated 2026 | Appropriated 2027 |
|---|---|---|---|---|---|
| 01-01-04 Operation and Maintenance of Historic SitesIn the current budget: A.1.4 HISTORIC SITES | $3,500,000 | $0 | — | $49,778,855 | $24,978,650 |
A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.
After 2029
The request marks this item as having no costs after 2029.
The agency's justification
Building on prior appropriations of $3.4 million, this project will create a new visitor center, enhance site landscaping, improve the visitor arrival sequence, and restore the historic Eisenhower home that currently serves as the visitor center. These improvements will strengthen interpretation of President Dwight D. Eisenhower’s legacy, expand storytelling opportunities focused on the surrounding historic neighborhood, and create a more welcoming and engaging experience for visitors. Additional funding will support an expanded project scope, including a feasibility study, visitation analysis, restoration of additional historic structures, and strategic land acquisition to improve site access and connectivity. These investments address needs identified through ongoing planning efforts and will ensure the site can accommodate future visitation growth while delivering enhanced interpretation, improved operational efficiency, and a cohesive, world-class visitor experience that supports heritage tourism and economic development in the region.
External and internal factors
Prior state appropriations of $3.4 million, identified facility and access needs, and anticipated future visitation growth require an expanded project scope to ensure the site can adequately serve visitors and protect historic resources. Additional investment will allow THC to address restoration, visitor circulation, land acquisition, and capacity needs as part of a coordinated project rather than through future piecemeal improvements.
As marked in the request
- Has an information technology part: No
- Costs anticipated after the two budget years: No
- Involves contracts over $50,000: Yes