Priority 20 · one of 21 items in the Historical Commission's request for 2028-29 · The item begins on page 186 of the request
This is a request, not an appropriation.
What is asked
| 2028 | 2029 | Two years | |
|---|---|---|---|
| All funds | $6,000,000 | $0 | $6,000,000 |
| Of which general revenue and general revenue-dedicated | $6,000,000 | $0 | $6,000,000 |
| Positions (full-time equivalents) | — | — |
How it would be financed
| Method of financing, as the request prints it | 2028 | 2029 |
|---|---|---|
| 1 General Revenue Fund | $6,000,000 | $0 |
| Total, as the request prints it | $6,000,000 | $0 |
Where it would land
The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.
| Strategy | Asked 2028 | Asked 2029 | Positions | Appropriated 2026 | Appropriated 2027 |
|---|---|---|---|---|---|
| 01-01-04 Operation and Maintenance of Historic SitesIn the current budget: A.1.4 HISTORIC SITES | $6,000,000 | $0 | — | $49,778,855 | $24,978,650 |
A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.
After 2029
The request marks this item as having no costs after 2029.
The agency's justification
The Iwo Jima SHS and Museum in the Lower Rio Grande Valley stands as a powerful tribute to the courage, sacrifice, and unity demonstrated by the men and women who served our nation. The proposed project includes construction of an auditorium and supporting spaces, including a community event venue capable of hosting private rentals, educational programs, and traveling exhibits, as well as 1,200 square feet of collection storage to support both current and future museum collections. The project is currently in the design phase in partnership with the Marine Military Academy. However, based on current construction cost estimates, existing funding is insufficient to provide the visitor services, collection care, and operational support necessary to meet modern museum standards. Additional funding is needed to ensure the facility can fully serve as a premier heritage tourism destination, preserve important historical resources, and enhance educational opportunities for Texans and visitors alike.
External and internal factors
Updated construction cost estimates indicate that existing project funding is insufficient to deliver the visitor services , collection storage, educational space, and operational support necessary to meet modern museum standards. Additional funding is required to address the construction funding gap and prevent reduction of critical project scope as the project advances through design.
As marked in the request
- Has an information technology part: No
- Costs anticipated after the two budget years: No
- Involves contracts over $50,000: Yes