Requests · Military Department

Jefferson County Readiness Center, State share of Planning and Design

Priority 11 · one of 16 items in the Military Department's request for 2028-29 · The item begins on page 114 of the request

This is a request, not an appropriation.

What is asked

20282029Two years
All funds$4,500,000$4,500,000$9,000,000
Of which general revenue and general revenue-dedicated $4,500,000$4,500,000$9,000,000
Positions (full-time equivalents) ——

How it would be financed

Method of financing, as the request prints it20282029
1 General Revenue Fund$4,500,000$4,500,000
Total, as the request prints it$4,500,000$4,500,000

Where it would land

The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.

Strategy Asked 2028Asked 2029Positions Appropriated 2026Appropriated 2027
02-01-01 Facilities Management and OperationsIn the current budget: B.1.1 FACILITIES MANAGEMENT & OPERATIONS $4,500,000$4,500,000— $96,124,809 $95,197,165
03-01-01 Train Youth in Specialized Education ProgramsIn the current budget: C.1.1 YOUTH EDUCATION PROGRAMS $0$0— $6,585,273 $6,585,273

A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.

After 2029

The request marks costs as anticipated after 2029 and shows no cost for 2030, 2031 or 2032.

In the agency's words: The FY2028 request funds the State share of planning and design only. A future construction phase is anticipated in connection with programmed federal MILCON funding in 2031, followed by recurring post-construction sustainment and operating costs. Future construction will require separate State and federal funding actions. After construction, eligible sustainment and operating costs are expected to receive 50 percent federal support.

The agency's justification

TMD requests $4,500,000 in General Revenue in FY 2028 for the State share of planning and design for a Capital Budget/Construction Project to build a new Texas Army National Guard Readiness Center in Jefferson County. The project supports Strategy B.1.1, Facilities Management and Operations, and advances TMD Strategic Goals 1 and 3: Enhance Responsiveness and Secure Texas. The federal MILCON program includes a programmed $23,000,000 federal construction share in 2031. State planning and design funds are needed in FY 2028 to secure matching federal planning/design participation, complete A/E design and environmental coordination, and place the project in a construction-ready position when federal funds are obligated. Jefferson County and the Beaumont–Port Arthur region form a strategic energy, petrochemical, refining, port, airport, and logistics corridor. The former Beaumont armory was divested in 2011, leaving Southeast Texas without a permanent TXARNG readiness center presence in a coastal region exposed to hurricanes, floods, industrial incidents, port disruption, and evacuation support missions. A modern Readiness Center Complex adjacent to Jack Brooks Regional Airport, on approximately 22 acres committed by Jefferson County through a long-term no-cost lease, will restore purpose-built Guard capability for training, unit administration, secure storage, staging, mobilization, and emergency response, aligning with Schedule L and the FORT Texas campaign.

External and internal factors

If unfunded, Texas will lack the State commitment needed to secure federal planning/design participation and move the Jefferson County Readiness Center project to construction readiness. Without completed design and environmental documentation, the project will not be ready to compete for or execute programmed 2031 federal MILCON construction funding, placing the $23,000,000 federal construction share at significant risk. Failure to fund also extends a known capability gap in Southeast Texas. Jefferson County and the Beaumont–Port Arthur region would remain without a modern TXARNG Readiness Center despite the area's importance to the Texas economy, Gulf Coast disaster response, energy security, petrochemical production, maritime commerce, and military logistics. The absence of a readiness center limits TMD's ability to train, stage, mobilize, and deploy personnel and equipment from within this critical coastal region and reduces the State's capacity to support civil authorities during hurricanes, floods, industrial emergencies, port disruptions, and evacuation operations. It also weakens recruiting, retention, and community presence in a major population and employment center. Funding this item protects Texas by leveraging federal MILCON investment, restoring National Guard capability in a strategically important region, and establishing the planning foundation for a secure, resilient facility.

As marked in the request