What is asked
| 2028 | 2029 | Two years | |
|---|---|---|---|
| All funds | $2,363,542 | $2,454,536 | $4,818,078 |
| Of which general revenue and general revenue-dedicated | $2,363,542 | $2,454,536 | $4,818,078 |
| Positions (full-time equivalents) | — | — |
How it would be financed
| Method of financing, as the request prints it | 2028 | 2029 |
|---|---|---|
| 1 General Revenue Fund | $2,363,542 | $2,454,536 |
| Total, as the request prints it | $2,363,542 | $2,454,536 |
Where it would land
The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.
| Strategy | Asked 2028 | Asked 2029 | Positions | Appropriated 2026 | Appropriated 2027 |
|---|---|---|---|---|---|
| 04-01-02 Information ResourcesIn the current budget: D.1.2 INFORMATION RESOURCES | $2,363,542 | $2,454,536 | — | $536,892 | $607,271 |
A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.
After 2029
| The agency's estimate | 2030 | 2031 | 2032 | Three years |
|---|---|---|---|---|
| All funds | $2,454,536 | $2,454,536 | $2,454,536 | $7,363,608 |
| Of which general revenue | $2,454,536 | $2,454,536 | $2,454,536 | $7,363,608 |
In the agency's words: Data Center Consolidation is an ongoing service requirement. Recurring costs for cloud infrastructure, hosting, storage, identity services, cybersecurity monitoring, backup, disaster recovery, licensing, and related support will continue after FY2029. Future costs will depend on Department of Information Resources pricing, service-provider rates, system consumption, data growth, and security requirements.
The agency's justification
The Texas Military Department requests $4,818,078 in General Revenue for FY 2028-2029 to fund projected Data Center Consolidation costs above the agency's existing capital-budget baseline. The request includes $2,363,542 in FY 2028 and $2,454,536 in FY 2029. Combined with existing baseline authority of $312,892 in FY 2028 and $361,271 in FY 2029, total projected Data Center Consolidation requirements are $2,676,434 and $2,815,807, respectively. The request supports Strategy D.1.2, Information Resources, and TMD's strategic goal to Promote Governance.
Data Center Consolidation provides the enterprise technology foundation required for TMD operations , including cloud infrastructure, Microsoft Exchange and Microsoft Entra services, application hosting, data storage, enterprise backup and disaster recovery, cybersecurity monitoring, and redundant computing resources. These services support the availability, security, and continuity of systems used for financial management, personnel administration, logistics, facilities management, communications, and other agency business functions.
The existing baseline does not support the projected cost of maintaining these enterprise services during the 2028-2029 biennium. The exceptional item does not create a new program or expand the agency's mission; it provides the funding required to continue existing services at the projected level of need. Without the requested increase, TMD would be required to absorb unavoidable data center costs within a limited Information Resources appropriation, increasing the likelihood of service reductions, deferred technology work, or diminished cybersecurity and business-continuity capability.
External and internal factors
External factors include Department of Information Resources and service-provider rate changes, increased cloud and storage consumption, software and licensing costs, evolving cybersecurity requirements, data growth, and the need for resilient and redundant technology services. These costs are affected by statewide contracts and enterprise service requirements that TMD cannot independently control.
Internal factors include increased dependence on cloud-hosted systems, identity and access management, secure remote connectivity, enterprise backup, disaster recovery, and continuous system availability. TMD must support a geographically dispersed organization and sustained operations while maintaining security and continuity for administrative and mission-support systems. A small existing baseline limits the agency's ability to absorb increases without reducing other technology services.
As marked in the request
- Has an information technology part: Yes
- Costs anticipated after the two budget years: Yes
- Involves contracts over $50,000: Yes