Requests · 2028-29

Office of Public Utility Counsel: what it asked for above the baseline

From the agency's Legislative Appropriations Request for 2028-29, whose summary schedule is dated 8/20/2026. The filing at the Legislative Budget Board · This agency in the current budget

These are requests, not appropriations.

Priority Item 2028 2029 Two years, all funds Of which general revenue Positions Estimated for 2030–2032
1 Restoration of Three-Percent Funding Reduction $158,437 $158,437 $316,874 $316,874 — $950,622
All items $158,437 $158,437 $316,874 $316,874 — $950,622

The request's summary also lists Exempt Position Change (priority 2) with no amounts and no item schedule.

Positions are full-time equivalents; where the two years differ the larger is shown. Costs for 2030 through 2032 are the agency's own estimates, for three years.

Rider changes asked for

1 row of the request's schedule 3.B was read. 1 is listed without marks, as under review. An existing rider's marks are shown only where they could be checked. A new rider's row is shown as the request prints it. How.

NumberedRider The agency asks toIn the request
2 not checked under reviewWith its additions removed, the language is not the rider as passed. page 30