Restoration of Three Percent Reduction
Priority 1 · one of 9 items in the Parks and Wildlife Department's request for 2028-29 · the item begins on page 245 of the PDF listed at the Legislative Budget Board's page for this filing
This is a request, not an appropriation.
What is asked
| 2028 | 2029 | Two years | |
|---|---|---|---|
| All funds | $9,816,065 | $3,866,065 | $13,682,130 |
| Of which general revenue and general revenue-dedicated | $9,816,065 | $3,866,065 | $13,682,130 |
| Positions (full-time equivalents) | — | — |
How it would be financed
| Method of financing, as the request prints it | 2028 | 2029 |
|---|---|---|
| 9 Game,Fish,Water Safety Ac | $5,491,000 | $0 |
| 64 State Parks Acct | $4,325,065 | $3,866,065 |
| Total, as the request prints it | $9,816,065 | $3,866,065 |
Where it would land
The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.
| Strategy | Asked 2028 | Asked 2029 | Positions | Appropriated 2026 | Appropriated 2027 |
|---|---|---|---|---|---|
| 02-01-01 State Parks, Historic Sites and State Natural Area OperationsIn the current budget: B.1.1 STATE PARK OPERATIONS | $3,866,065 | $3,866,065 | — | $130,117,742 | $128,290,601 |
| 04-01-01 Implement Capital Improvements and Major RepairsIn the current budget: D.1.1 IMPROVEMENTS AND MAJOR REPAIRS | $5,950,000 | $0 | — | $49,955,000 | $54,605,000 |
A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.
After 2029
| The agency's estimate | 2030 | 2031 | 2032 | Three years |
|---|---|---|---|---|
| All funds | $3,866,065 | $3,866,065 | $3,866,065 | $11,598,195 |
In the agency's words: Reflects ongoing costs for daily operations, maintaining core services and addressing increased usage and expansion of the State Parks system.
The agency's justification
TPWD’s GR/GRD limits included a three percent reduction in base level funding. TPWD is requesting restoration of funding for state park operations and capital construction.
State parks operating is critical to TPWD due to additional parks being added to the State Parks system and continued increases in state park visitation . With the addition of Post Oak Ridge and Bear Creek in the upcoming biennium, as well as other parks with staggered openings and public access, it is imperative that state parks have the funding to fully operate new and existing parks to maintain and enhance core services.
TPWD is requesting $7.7M over the biennium for cost increases & operational needs including utilities, fuel, travel, consumable supplies, etc. related to existing and new parks.
TPWD is entrusted with the maintenance and repair of agency facilities. Current facilities are aging and the backlog of repairs continues to grow. TPWD is requesting the restoration of capital construction funds for the following:
• Austin HQ Utility & Security; $900,000 of GRD 9 & 64. • A.E. Wood Fish Hatchery Concrete Repairs; $2M of GRD 9; Freshwater Fish Stamp.
• Perry R Bass Research Center Replacement of Sea Water Intake; $2.5M of GRD 9; Saltwater Fish Stamp. • Gus Engeling Wildlife Management Area Replacement of Storage Barns; $50,000 of GRD 9. • Texas Game Warden Training Center Facility Repairs; $500,000 of GRD 9.
External and internal factors
With the full dedication and increases in Sporting Goods Sales Tax and the passage of the Centennial Parks Conservation Fund , State Parks has been able to expand and accelerate the opening of new and renovation to existing state parks. With expanded access to the State Parks system, TPWD must be able to fully operate these parks as they come online. Without adequate funding, TPWD cannot provide the customer experience that the people of Texas expect and deserve.
Construction and repair needs continue to be identified with each passing year as structures deteriorate and/or become outdated. Additionally, many factors beyond TPWD control, such as economic conditions, catastrophic weather, natural disasters, and permit/study requirements, can impact the agency's capital construction and repair program. Lack of adequate funding for TPWD facilities hampers the ability to carry out the department’s mission and goals of making reliable science -based conservation and management decisions, providing public hunting, fishing and wildlife viewing opportunities, and carrying out other conservation enforcement and public safety priorities.
As marked in the request
- Has an information technology part: No
- Costs anticipated after the two budget years: Yes
- Involves contracts over $50,000: Yes