Requests · Parks and Wildlife Department

Capital Transportation

Priority 2 · one of 9 items in the Parks and Wildlife Department's request for 2028-29 · the item begins on page 248 of the PDF listed at the Legislative Budget Board's page for this filing

This is a request, not an appropriation.

What is asked

20282029Two years
All funds$24,354,875$19,156,717$43,511,592
Of which general revenue and general revenue-dedicated $24,354,875$19,156,717$43,511,592
Positions (full-time equivalents) ——

How it would be financed

Method of financing, as the request prints it20282029
1 General Revenue Fund$24,354,875$19,156,717
Total, as the request prints it$24,354,875$19,156,717

Where it would land

The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.

Strategy Asked 2028Asked 2029Positions Appropriated 2026Appropriated 2027
01-01-01 Wildlife Conservation, Habitat Management, and ResearchIn the current budget: A.1.1 WILDLIFE CONSERVATION $2,772,161$12,161— $38,126,887 $38,126,886
01-02-01 Inland Fisheries Management, Habitat Conservation, and ResearchIn the current budget: A.2.1 INLAND FISHERIES MANAGEMENT $901,347$926,847— $18,076,127 $18,098,127
01-02-02 Inland Hatcheries OperationsIn the current budget: A.2.2 INLAND HATCHERIES OPERATIONS $387,400$387,400— $8,558,352 $8,536,351
01-02-03 Coastal Fisheries Management, Habitat Conservation and ResearchIn the current budget: A.2.3 COASTAL FISHERIES MANAGEMENT $686,285$171,285— $15,517,003 $15,517,002
01-02-04 Coastal Hatcheries OperationsIn the current budget: A.2.4 COASTAL HATCHERIES OPERATIONS $102,000$102,000— $5,245,908 $5,245,908
02-01-01 State Parks, Historic Sites and State Natural Area OperationsIn the current budget: B.1.1 STATE PARK OPERATIONS $4,336,104$2,423,364— $130,117,742 $128,290,601
03-01-01 Wildlife, Fisheries and Water Safety Enforcement/EducationIn the current budget: C.1.1 ENFORCEMENT PROGRAMS $15,058,660$15,058,660— $106,695,323 $106,152,039
03-02-02 Provide Communication Products and ServicesIn the current budget: C.2.2 PROVIDE COMMUNICATION PRODUCTS $35,918$0— $5,846,546 $5,846,545
04-01-03 Infrastructure Program AdministrationIn the current budget: D.1.3 INFRASTRUCTURE ADMINISTRATION $75,000$75,000— $9,124,834 $9,124,833

A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.

After 2029

The agency's estimate203020312032Three years
All funds$20,608,262$20,608,262$20,608,262$61,824,786
Of which general revenue$20,608,262$20,608,262$20,608,262$61,824,786

In the agency's words: Costs are tied to ensure agency replacement schedules and on-going needs are met for both vehicles, boats, and UTVs.

The agency's justification

TPWD’s GR/GRD limit approved by LBB and GOBP reduced authority tied to all TPWD capital transportation, including vehicles, boats, and UTVs, except those exclusively funded with Sporting Goods Sales Tax. This includes vehicles associated with law enforcement and those tied to Rider 13 border security activities.

TPWD is dependent on safe, reliable and well-maintained vehicles to continue critical ongoing operations across the state and provide mission critical services to the people of Texas. These activities include responding to natural disasters and swift water rescue, providing support to border counties, New World Screwworm response and monitoring, conducting wildlife and aquatic biological studies, providing wildlife technical guidance to private landowners, operating state parks and WMAs, providing outreach and education services, managing construction projects, responding to violations and accidents involving natural resources, mail delivery, maintenance of facilities and security, and more. Agency vehicles are utilized heavily and must be replaced according to an ongoing/recurring replacement schedule.

This request would provide capital transportation authority to allow TPWD to replace vehicles according to schedule to ensure safety and reliability . This request will also allow TPWD to secure additional vehicles needed for new state parks coming online in the upcoming biennium and additional vehicles and boats to support fisheries and wildlife activities.

External and internal factors

It is crucial for TPWD to have ongoing capital transportation authority to replace vehicles as they meet/exceed state and agency replacement thresholds. Delays in the ability to replace vehicles could result in unsafe and unreliable equipment, possible interruption of services, and increased repair expenses.

Likewise, as the number of state parks begins to grow, TPWD requires additional vehicles for staff at those locations to effectively carry out their duties.

The Office of Vehicle Fleet Management “Texas State Vehicle Fleet Management Plan” specifies that passenger vehicles should be evaluated for replacement at 9 years of service and 100,000 miles, while it recommends that cargo vehicles should be replaced at 10 years and 110,000 miles. TPWD follows these general guidelines for most vehicle replacement schedules, however, given the complexity of TPWD's vehicle fleet and various uses, other factors are at times also considered, such as usage, condition, maintenance and repair costs, and availability of budget/authority.

As marked in the request