Priority 6 · one of 9 items in the Parks and Wildlife Department's request for 2028-29 · the item begins on page 263 of the PDF listed at the Legislative Budget Board's page for this filing
This is a request, not an appropriation.
What is asked
| 2028 | 2029 | Two years | |
|---|---|---|---|
| All funds | $3,319,400 | $2,758,400 | $6,077,800 |
| Of which general revenue and general revenue-dedicated | $3,319,400 | $2,758,400 | $6,077,800 |
| Positions (full-time equivalents) | 22.0 | 22.0 |
How it would be financed
| Method of financing, as the request prints it | 2028 | 2029 |
|---|---|---|
| 1 General Revenue Fund | $3,319,400 | $2,758,400 |
| Total, as the request prints it | $3,319,400 | $2,758,400 |
Where it would land
The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.
| Strategy | Asked 2028 | Asked 2029 | Positions | Appropriated 2026 | Appropriated 2027 |
|---|---|---|---|---|---|
| 01-01-01 Wildlife Conservation, Habitat Management, and ResearchIn the current budget: A.1.1 WILDLIFE CONSERVATION | $3,319,400 | $2,758,400 | 22.0 | $38,126,887 | $38,126,886 |
A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.
After 2029
The request marks this item as having no costs after 2029.
The agency's justification
New World Screwworm was first confirmed in Texas on June 3, 2026. Since then, TPWD, Animal Health Commission, and Texas leadership have formed the Texas New World Response Team to combat and minimize the spread of the fly and infected wildlife. Since June 2026, TPWD has remained on the forefront of response, surveillance, removal & disposal of infested native wildlife, and inspection and treatment of wildlife prior to movement.
This request would provide $6.1M over the biennium for continued efforts to combat the spread of New World Screwworm. Included in this ask is funding for 22 temporary full-time Fish & Wildlife Technicians, equipment, vehicles, & necessary operating for these positions. TPWD anticipates this request for only a biennium and is not requesting funding past AY29.
This funding is necessary to ensure the safety and health of domestic and wild animals in the state of Texas.
External and internal factors
New World Screwworm is a complex situation and requires a coordinated and calculated approach. Factors outside the control of TPWD include animals moving freely through infection zones and detection being difficult in wild populations. TPWD is on the Texas New World Response Team along with The Animal Health Commission. This Response Team provides coordinated responses, surveillance & training, and public resources to slow and monitor the spread of New World Screwworm.
Currently the federal government is building and expanding a New World Screwworm facility to combat and reduce the threat to Texas , but until the facility is at full capacity, TPWD must be in a position to monitor, respond and minimize the spread of this threat.
As marked in the request
- Has an information technology part: No
- Costs anticipated after the two budget years: No
- Involves contracts over $50,000: Yes