Priority 2 · one of 3 items in the Preservation Board's request for 2028-29 · The item begins on page 108 of the request

This is a request, not an appropriation.

What is asked

20282029Two years
All funds$31,800,000$0$31,800,000
Of which general revenue and general revenue-dedicated $31,800,000$0$31,800,000
Positions (full-time equivalents) ——

How it would be financed

Method of financing, as the request prints it20282029
1 General Revenue Fund$31,800,000$0
Total, as the request prints it$31,800,000$0

Where it would land

The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.

Strategy Asked 2028Asked 2029Positions Appropriated 2026Appropriated 2027
01-01-02 Maintain State Capitol and Other Designated Buildings and GroundsIn the current budget: A.1.2 BUILDING MAINTENANCE $21,000,000$0— $7,740,702 $7,931,811
01-02-02 Manage and Operate the Bob Bullock Texas State History MuseumIn the current budget: A.2.2 MANAGE STATE HISTORY MUSEUM $10,800,000$0— $5,443,367 $1,943,367

A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.

After 2029

The request marks costs as anticipated after 2029 and shows no cost for 2030, 2031 or 2032.

The agency's justification

The request is to upgrade and replace aging and increasing unreliable fire alarm systems that create increase maintenance needs and operational risks to state investments.

External and internal factors

Age and reliability of current fire alarm systems, the need to protect visitors, staff, exhibits, and irreplaceable historical collections, and the operational disruptions associated with system failures.

As marked in the request