Requests · Railroad Commission
Oil and Gas Staffing
Priority 3 · one of 9 items in the Railroad Commission's request for 2028-29 · The item begins on page 110 of the request
This is a request, not an appropriation.
What is asked
| 2028 | 2029 | Two years | |
|---|---|---|---|
| All funds | $1,815,786 | $1,815,786 | $3,631,572 |
| Of which general revenue and general revenue-dedicated | $1,815,786 | $1,815,786 | $3,631,572 |
| Positions (full-time equivalents) | 5.0 | 5.0 |
How it would be financed
| Method of financing, as the request prints it | 2028 | 2029 |
|---|---|---|
| 1 General Revenue Fund | $1,815,786 | $1,815,786 |
| Total, as the request prints it | $1,815,786 | $1,815,786 |
Where it would land
The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.
| Strategy | Asked 2028 | Asked 2029 | Positions | Appropriated 2026 | Appropriated 2027 |
|---|---|---|---|---|---|
| 03-01-01 Oil and Gas Monitoring and InspectionsIn the current budget: C.1.1 OIL/GAS MONITOR & INSPECTIONS | $1,815,786 | $1,815,786 | 5.0 | $35,310,146 | $35,646,776 |
A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.
After 2029
| The agency's estimate | 2030 | 2031 | 2032 | Three years |
|---|---|---|---|---|
| All funds | $815,786 | $815,786 | $815,786 | $2,447,358 |
In the agency's words: These anticipated out-year costs are the on-going salaries for the requested FTE's
The agency's justification
RRC District Offices need additional staff for field work, enforcement activities, and administrative support. The staff at the district offices has not keep pace with the oil and gas industry activity. RRC will need additional inspectors in order to maintain the statutory five year inspections on all wells and to quickly respond to landowner concerns regarding spills, unsafe electrical equipment, and reports of oil theft.
External and internal factors
Internal Factors: RRC District Offices staffing levels have not increased with industry activity. Additional staff is necessary to ensure timely inspections and enforcement of safety concerns to reduce environmental risk. External Factors:Despite the fluctuation of the price of oil over the last several years, the oil and gas industry has been steadily growing. The creates additional work and requires additional RRC staff to keep pace. The responsibilities of the districts have increased with additional legislative for Inactive Wells and removal of electrical equipment. The districts have responded to more landowner concerns about wildfire safety due to recent fires in the panhandle.
As marked in the request
- Has an information technology part: No
- Costs anticipated after the two budget years: Yes
- Involves contracts over $50,000: No