Requests · Sam Houston State University
Science & Engineering Technology Complex
Priority 2 · one of 4 items in the Sam Houston State University's request for 2028-29 · The item begins on page 108 of the request
This is a request, not an appropriation.
What is asked
| 2028 | 2029 | Two years | |
|---|---|---|---|
| All funds | $12,900,000 | $12,900,000 | $25,800,000 |
| Of which general revenue and general revenue-dedicated | $12,900,000 | $12,900,000 | $25,800,000 |
| Positions (full-time equivalents) | — | — |
How it would be financed
| Method of financing, as the request prints it | 2028 | 2029 |
|---|---|---|
| 1 General Revenue Fund | $12,900,000 | $12,900,000 |
| Total, as the request prints it | $12,900,000 | $12,900,000 |
Where it would land
The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.
| Strategy | Asked 2028 | Asked 2029 | Positions | Appropriated 2026 | Appropriated 2027 |
|---|---|---|---|---|---|
| 02-01-02 Capital Construction Assistance Projects Revenue Bonds | $12,900,000 | $12,900,000 | — | No strategy matched in the current budget | |
A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.
After 2029
| The agency's estimate | 2030 | 2031 | 2032 | Three years |
|---|---|---|---|---|
| All funds | $12,900,000 | $12,900,000 | $12,900,000 | $38,700,000 |
In the agency's words: The out-year costs for the proposed Science & Engineering Technology Complex at Sam Houston State University are necessary to service the debt on the revenue bonds used to finance the construction of this critical facility.
The agency's justification
Growth in science, engineering technology, and agricultural programs has increased the need for specialized instructional and laboratory space at SHSU. The University’s 2023 Campus Master Plan projects a 100,000 net assignable square foot academic space deficit within the College of Science & Engineering Technology (COSET), with the greatest needs in Engineering Technology and Agricultural Sciences.
To address this constraint, SHSU proposes a 111,000 gross square foot Science & Engineering Technology Complex along with a 1,500 TON central plant adjacent to the existing Fred Pirkle Engineering Technology Center. The facility would provide the specialized laboratories and instructional spaces necessary to support continued growth in these programs.
The proposed investment would address a documented academic space need while expanding SHSU’s capacity to educate students in science, engineering technology, agriculture, and other high-demand fields that are essential to Texas’ continued economic growth and competitiveness.
External and internal factors
A demographic analysis prepared for SHSU’s 2023 Campus Master Plan projects the total population of SHSU’s primary recruitment area will grow 2.3% by 2031, far exceeding statewide and national growth projections. Enrollment at SHSU’s Huntsville Campus is projected to grow by 13% over the same period, with the planned expansion of Science and Engineering Technology programs contributing to this growth . At present, Agriculture, Computer Science, and Engineering Technology programs are housed in multiple buildings throughout the Huntsville Campus. The construction of the Science & Engineering Technology Complex will increase opportunities for interdisciplinary and cross-disciplinary collaboration between students and faculty through the consolidation of these and other COSET programs within the new facility and adjacent COSET buildings.
As marked in the request
- Has an information technology part: No
- Costs anticipated after the two budget years: Yes
- Involves contracts over $50,000: No