From the agency's Legislative Appropriations Request for 2028-29, whose summary schedule is dated 8/10/2026. The document read · The filing at the Legislative Budget Board · This agency in the current budget

These are requests, not appropriations.

Priority Item 2028 2029 Two years, all funds Of which general revenue Positions Estimated for 2030–2032
1 Texas RAPID (Rapid Advanced Prototyping Innovations and Deployment) $30,270,000 $44,730,000 $75,000,000 $75,000,000 2.0 $15,000,000
2 Restore the 3% General Revenue Baseline Reduction $874,226 $874,270 $1,748,496 $1,748,496 — $2,622,741
3 Capstone for Biomanufacturing Workforce Development $4,000,000 $4,000,000 $8,000,000 $8,000,000 2.0 $12,000,000
All items $35,144,226 $49,604,270 $84,748,496 $84,748,496 4.0 $29,622,741

Positions are full-time equivalents; where the two years differ the larger is shown. Costs for 2030 through 2032 are the agency's own estimates, for three years.

Rider changes asked for

5 rows of the request's schedule 3.B were read. 3 are shown with the agency's marks: 0 to keep as they are, 0 to update the years only, 2 to revise, 0 to delete and 1 to add.2 are listed without marks, as under review. An existing rider's marks are shown only where they could be checked. A new rider's row is shown as the request prints it. How.

NumberedRider The agency asks toIn the request
new Texas RAPID add as a new rider page 68
3 Offshore Technology Research CenterReduced amount by 3% to address impact of required 3% budget reduction. revise page 68
4 Nuclear Engineering and Secure ManufacturingReduced amount by 3% to address impact of required 3% budget reduction. revise page 69
6 not checked under reviewWith its additions removed, the language is not the rider as passed. page 69
9 not checked under reviewWith its additions removed, the language is not the rider as passed. page 69