Requests · Texas State Technical College System Administration

Comal County/Guadalupe County - Building and Infrastructure

Priority 2 · one of 12 items in the Texas State Technical College System Administration's request for 2028-29 · the item begins on page 195 of the PDF listed at the Legislative Budget Board's page for this filing

This is a request, not an appropriation.

What is asked

20282029Two years
All funds$7,014,580$7,014,580$14,029,160
Of which general revenue and general revenue-dedicated $7,014,580$7,014,580$14,029,160
Positions (full-time equivalents) ——

How it would be financed

Method of financing, as the request prints it20282029
1 General Revenue Fund$7,014,580$7,014,580
Total, as the request prints it$7,014,580$7,014,580

Where it would land

The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.

Strategy Asked 2028Asked 2029Positions Appropriated 2026Appropriated 2027
01-02-02 Capital Construction Assistance Projects Revenue Bonds $7,014,580$7,014,580—No strategy matched in the current budget

A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.

After 2029

The agency's estimate203020312032Three years
All funds$7,014,580$7,014,580$7,014,580$21,043,740

In the agency's words: Debt service for CCAP's are set for the term of the bond, which is 20 years. tstc.edu 191

The agency's justification

New 130,000 SF campus building and infrastructure on undeveloped site supporting Manufacturing and Construction programs

External and internal factors

Consequences of not funding: Reduced capacity for reducing Texas' skills shortage.

As marked in the request