Requests · Texas State Technical College System Administration
Harlingen - Welding Training Laboratory
Priority 4 · one of 12 items in the Texas State Technical College System Administration's request for 2028-29 · the item begins on page 199 of the PDF listed at the Legislative Budget Board's page for this filing
This is a request, not an appropriation.
What is asked
| 2028 | 2029 | Two years | |
|---|---|---|---|
| All funds | $1,571,186 | $1,571,186 | $3,142,372 |
| Of which general revenue and general revenue-dedicated | $1,571,186 | $1,571,186 | $3,142,372 |
| Positions (full-time equivalents) | — | — |
How it would be financed
| Method of financing, as the request prints it | 2028 | 2029 |
|---|---|---|
| 1 General Revenue Fund | $1,571,186 | $1,571,186 |
| Total, as the request prints it | $1,571,186 | $1,571,186 |
Where it would land
The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.
| Strategy | Asked 2028 | Asked 2029 | Positions | Appropriated 2026 | Appropriated 2027 |
|---|---|---|---|---|---|
| 04-02-02 Capital Construction Assistance Projects Revenue Bonds | under review | No strategy matched in the current budget | |||
A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.
After 2029
| The agency's estimate | 2030 | 2031 | 2032 | Three years |
|---|---|---|---|---|
| All funds | $1,571,186 | $1,571,186 | $1,571,186 | $4,713,558 |
In the agency's words: Debt service for CCAP's are set for the term of the bond, which is 20 years. tstc.edu 195
The agency's justification
Welding is a foundational, high-placement program running at capacity, with demand spanning energy, manufacturing, and construction. In addition, the Rio Grande Valley has seen significant investment in the Port of Brownsville and new investment by Saronic, a ship building company, means demand for welders will grow rapidly.
Completely repurpose an existing classroom building to a full-scale, 70,000 square foot welding training lab will significantly expand welding capacity in Harlingen to serve South Texas industry.
External and internal factors
Consequences of not funding: Reduced capacity for reducing Texas' skills shortage.
As marked in the request
- Has an information technology part: No
- Costs anticipated after the two budget years: Yes
- Involves contracts over $50,000: No