This is a request, not an appropriation.

What is asked

20282029Two years
All funds$7,014,580$7,014,580$14,029,160
Of which general revenue and general revenue-dedicated $7,014,580$7,014,580$14,029,160
Positions (full-time equivalents) ——

How it would be financed

Method of financing, as the request prints it20282029
1 General Revenue Fund$7,014,580$7,014,580
Total, as the request prints it$7,014,580$7,014,580

Where it would land

The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.

Strategy Asked 2028Asked 2029Positions Appropriated 2026Appropriated 2027
06-02-02 Capital Construction Assistance Projects Revenue Bonds under review No strategy matched in the current budget

A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.

After 2029

The agency's estimate203020312032Three years
All funds$7,014,580$7,014,580$7,014,580$21,043,740

In the agency's words: Debt service for CCAP's are set for the term of the bond, which is 20 years. tstc.edu 209

The agency's justification

Midlothian – New 130,000 SF campus building and infrastructure

External and internal factors

Consequences of not funding: Reduced capacity for reducing Texas' skills shortage.