Requests · Texas State University
Debt Service for CCAP Bonds
Priority 9 · one of 9 items in the Texas State University's request for 2028-29 · the item begins on page 103 of the PDF listed at the Legislative Budget Board's page for this filing
This is a request, not an appropriation.
What is asked
| 2028 | 2029 | Two years | |
|---|---|---|---|
| All funds | $19,350,000 | $19,350,000 | $38,700,000 |
| Of which general revenue and general revenue-dedicated | $19,350,000 | $19,350,000 | $38,700,000 |
| Positions (full-time equivalents) | — | — |
How it would be financed
| Method of financing, as the request prints it | 2028 | 2029 |
|---|---|---|
| 1 General Revenue Fund | $19,350,000 | $19,350,000 |
| Total, as the request prints it | $19,350,000 | $19,350,000 |
Where it would land
The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.
| Strategy | Asked 2028 | Asked 2029 | Positions | Appropriated 2026 | Appropriated 2027 |
|---|---|---|---|---|---|
| 02-01-02 Capital Construction Assistance Projects Revenue Bonds | $19,350,000 | $19,350,000 | — | No strategy matched in the current budget | |
A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.
After 2029
| The agency's estimate | 2030 | 2031 | 2032 | Three years |
|---|---|---|---|---|
| All funds | $19,350,000 | $19,350,000 | $19,350,000 | $58,050,000 |
| Of which general revenue | $19,350,000 | $19,350,000 | $19,350,000 | $58,050,000 |
In the agency's words: Anticipated out year cost is continued debt service payments for the life of the bond issuance. 101 90th Regular Session, Agency Submission, Version 1 TIME: 11:30:48AM
The agency's justification
This funding is for the debt service payment on the capital construction assistance project bonds that will be used to construct a Science and Research Building ($12,900,000 in annual debt service based on $150 million in CCAP towards a $226.8 million total cost) on the San Marcos Campus and a new multi-purpose Commons Building ($6,450,000 in annual debt service based on $75 million in CCAP towards a $110 million total cost) on the Round Rock Campus.
External and internal factors
Interest rates on tax-exempt bonds could change by the time the appropriation is ultimately made and thereby impact the cost of the strategy.
As marked in the request
- Has an information technology part: No
- Costs anticipated after the two budget years: Yes
- Involves contracts over $50,000: No