Requests · Texas State University

Debt Service for CCAP Bonds

Priority 9 · one of 9 items in the Texas State University's request for 2028-29 · the item begins on page 103 of the PDF listed at the Legislative Budget Board's page for this filing

This is a request, not an appropriation.

What is asked

20282029Two years
All funds$19,350,000$19,350,000$38,700,000
Of which general revenue and general revenue-dedicated $19,350,000$19,350,000$38,700,000
Positions (full-time equivalents) ——

How it would be financed

Method of financing, as the request prints it20282029
1 General Revenue Fund$19,350,000$19,350,000
Total, as the request prints it$19,350,000$19,350,000

Where it would land

The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.

Strategy Asked 2028Asked 2029Positions Appropriated 2026Appropriated 2027
02-01-02 Capital Construction Assistance Projects Revenue Bonds $19,350,000$19,350,000—No strategy matched in the current budget

A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.

After 2029

The agency's estimate203020312032Three years
All funds$19,350,000$19,350,000$19,350,000$58,050,000
Of which general revenue$19,350,000$19,350,000$19,350,000$58,050,000

In the agency's words: Anticipated out year cost is continued debt service payments for the life of the bond issuance. 101 90th Regular Session, Agency Submission, Version 1 TIME: 11:30:48AM

The agency's justification

This funding is for the debt service payment on the capital construction assistance project bonds that will be used to construct a Science and Research Building ($12,900,000 in annual debt service based on $150 million in CCAP towards a $226.8 million total cost) on the San Marcos Campus and a new multi-purpose Commons Building ($6,450,000 in annual debt service based on $75 million in CCAP towards a $110 million total cost) on the Round Rock Campus.

External and internal factors

Interest rates on tax-exempt bonds could change by the time the appropriation is ultimately made and thereby impact the cost of the strategy.

As marked in the request