Requests · Texas Tech University Health Sciences Center

Capital Construction Assistance Projects

Priority 3 · one of 5 items in the Texas Tech University Health Sciences Center's request for 2028-29 · The item begins on page 139 of the request

This is a request, not an appropriation.

What is asked

20282029Two years
All funds$7,846,610$7,846,610$15,693,220
Of which general revenue and general revenue-dedicated $7,846,610$7,846,610$15,693,220
Positions (full-time equivalents) ——

How it would be financed

Method of financing, as the request prints it20282029
1 General Revenue Fund$7,846,610$7,846,610
Total, as the request prints it$7,846,610$7,846,610

Where it would land

The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.

Strategy Asked 2028Asked 2029Positions Appropriated 2026Appropriated 2027
03-02-01 Capital Construction Assistance Projects Revenue Bonds $7,846,610$7,846,610—No strategy matched in the current budget

A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.

After 2029

The agency's estimate203020312032Three years
All funds$7,846,610$7,846,610$7,846,610$23,539,830

In the agency's words: Ongoing funding for CCAP debt service.

The agency's justification

This project is to construct an Amarillo Workforce Development Center. There are 335 students enrolled at the Amarillo campus including students in Medicine (109); Allied Health (51); Nursing (76); Pharmacy (82) and Graduate School of Biomedical Sciences (17) in addition to 98 Graduate Medical Education residents. The project is particularly critical to supporting growth in high-demand workforce programs, including nursing and allied health disciplines, where enrollment demand continues to exceed available training capacity.

The Workforce Development Center will replace an obsolete, off-campus facility that currently houses academic and administrative functions. It will also allow TTUHSC to vacate an obsolete facility with significant deferred maintenance requirements and relocate its occupants and programs to a modern, purpose-built building located on the primary campus.

The total cost is $100,000,000 with the source of funding as follows: -CCAP Bonds - $90,000,000 -Funds Other Than CCAP - $10,000,000 Debt Service: -2028: $7,846,610 -2029: $7,846,610

As marked in the request