Requests · 2028-29

Texas Woman's University: what it asked for above the baseline

From the agency's Legislative Appropriations Request for 2028-29, whose summary schedule is dated 10/16/2026. The filing at the Legislative Budget Board · This agency in the current budget

These are requests, not appropriations.

Priority Item 2028 2029 Two years, all funds Of which general revenue Positions Estimated for 2030–2032
1 Institutional Transformation Additional Funding $3,500,000 $3,500,000 $7,000,000 $7,000,000 45.0 $15,000,000
2 Mechanical Engineering Degree Program Expansion $1,500,000 $1,500,000 $3,000,000 $3,000,000 15.0 $4,500,000
3 Aviation Program Aircraft Procurement and Maintenance $2,150,000 $2,150,000 $4,300,000 $4,300,000 2.0 $450,000
4 Restoration of 3% Proposed Cut $593,464 $593,464 $1,186,928 $1,186,928 — $1,780,392
5 Capital Construction – Engineering and STEM Building $13,514,519 $13,514,519 $27,029,038 $27,029,038 — $40,543,557
All items $21,257,983 $21,257,983 $42,515,966 $42,515,966 62.0 $62,273,949

The request's summary also lists Texas Healthcare Fund (priority 6) with no amounts and no item schedule.

Positions are full-time equivalents; where the two years differ the larger is shown. Costs for 2030 through 2032 are the agency's own estimates, for three years.

Rider changes asked for

1 row of the request's schedule 3.B was read. 1 is listed without marks, as under review. An existing rider's marks are shown only where they could be checked. A new rider's row is shown as the request prints it. How.

NumberedRider The agency asks toIn the request
1 not checked under reviewThe marks drawn on the page and the marks seen in its image do not agree somewhere in this row, so they are not shown. page 80