What is asked
| 2028 | 2029 | Two years | |
|---|---|---|---|
| All funds | $13,080,000 | $13,080,000 | $26,160,000 |
| Of which general revenue and general revenue-dedicated | $13,080,000 | $13,080,000 | $26,160,000 |
| Positions (full-time equivalents) | — | — |
How it would be financed
| Method of financing, as the request prints it | 2028 | 2029 |
|---|---|---|
| 1 General Revenue Fund | $13,080,000 | $13,080,000 |
| Total, as the request prints it | $13,080,000 | $13,080,000 |
Where it would land
The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.
| Strategy | Asked 2028 | Asked 2029 | Positions | Appropriated 2026 | Appropriated 2027 |
|---|---|---|---|---|---|
| 02-01-02 Capital Construction Assistance Projects Revenue Bonds | $13,080,000 | $13,080,000 | — | No strategy matched in the current budget | |
A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.
After 2029
| The agency's estimate | 2030 | 2031 | 2032 | Three years |
|---|---|---|---|---|
| All funds | $13,080,000 | $13,080,000 | $13,080,000 | $39,240,000 |
In the agency's words: Out-year costs include meeting debt service needs. There should be decreases in operational costs to the University from reduced utilities and maintenance.
The agency's justification
The University of Texas Permian Basin (UTPB) Midland Campus currently houses the College of Engineering, the Center for Energy and Economic Diversification, and the Wagner Noel Performing Arts Center. Expanding the campus will strengthen UTPB's support for Midland and the Permian Basin by increasing academic, research, and workforce development activities.
The project includes approximately 178,000 gross square feet of new construction and renovation for teaching, research, student collaboration, and multipurpose space. Depending on the final campus plan, UTPB may construct new facilities, renovate existing buildings, or both. The project will also include utility infrastructure to support future campus growth and expand programs in engineering, science, and the arts.
As marked in the request
- Has an information technology part: No
- Costs anticipated after the two budget years: Yes