From the agency's Legislative Appropriations Request for 2028-29, whose summary schedule is dated 10/8/2026. The document read · The filing at the Legislative Budget Board · This agency in the current budget

These are requests, not appropriations.

Priority Item 2028 2029 Two years, all funds Of which general revenue Positions Estimated for 2030–2032
1 Debt Service for CCAP Funding for New Education Building - School of Public Health & School of Health Professions Academic Center $13,080,000 $13,080,000 $26,160,000 $26,160,000 — $39,240,000
2 3% Restoration $410,767 $410,767 $821,534 $821,534 — none reported
All items $13,490,767 $13,490,767 $26,981,534 $26,981,534 — $39,240,000

Positions are full-time equivalents; where the two years differ the larger is shown. Costs for 2030 through 2032 are the agency's own estimates, for three years.

Rider changes asked for

2 rows of the request's schedule 3.B were read. 2 are listed without marks, as under review. An existing rider's marks are shown only where they could be checked. A new rider's row is shown as the request prints it. How.

NumberedRider The agency asks toIn the request
4 not checked under reviewWith its additions removed, the language is not the rider as passed. page 94