Requests · University of Houston - Clear Lake

UHCL Campus Modernization and Workforce Dev. Initiative

Priority 2 · one of 3 items in the University of Houston - Clear Lake's request for 2028-29 · the item begins on page 74 of the PDF listed at the Legislative Budget Board's page for this filing

This is a request, not an appropriation.

What is asked

20282029Two years
All funds$16,014,511$16,014,511$32,029,022
Of which general revenue and general revenue-dedicated $16,014,511$16,014,511$32,029,022
Positions (full-time equivalents) ——

How it would be financed

Method of financing, as the request prints it20282029
1 General Revenue Fund$16,014,511$16,014,511
Total, as the request prints it$16,014,511$16,014,511

Where it would land

The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.

Strategy Asked 2028Asked 2029Positions Appropriated 2026Appropriated 2027
02-01-02 Capital Construction Assistance Projects Revenue Bonds $16,014,511$16,014,511—No strategy matched in the current budget

A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.

After 2029

The agency's estimate203020312032Three years
All funds$16,014,511$16,014,511$16,014,511$48,043,533

In the agency's words: Annual out-year costs represent CCAP debt service and routine operating and maintenance expenses associated with new and renovated facilities. UHCL will incorporate these recurring costs into future operating budgets and continue to maintain the facilities as long-term state assets.

The agency's justification

The University of Houston–Clear Lake requests CCAP funding for the UHCL Campus Modernization and Workforce Development Initiative . This coordinated capital investment will expand workforce education capacity through construction of the STEM II Academic and Laboratory Building , build-out of the Behavioral Health Workforce & Clinical Services Center at UHCL at Pearland, and renovation of the Delta Building. Together, these projects will modernize aging facilities, expand instructional and clinical space, strengthen workforce development in high-demand fields, improve operational efficiency, and maximize prior state investments through strategic reuse of existing campus infrastructure.

External and internal factors

Consequence of not funding

As marked in the request