Advanced Manufacturing Bldg
Priority 3 · one of 4 items in the University of Houston's request for 2028-29 · The item begins on page 86 of the request
This is a request, not an appropriation.
What is asked
| 2028 | 2029 | Two years | |
|---|---|---|---|
| All funds | $19,616,513 | $19,616,512 | $39,233,025 |
| Of which general revenue and general revenue-dedicated | $19,616,513 | $19,616,512 | $39,233,025 |
| Positions (full-time equivalents) | — | — |
How it would be financed
| Method of financing, as the request prints it | 2028 | 2029 |
|---|---|---|
| 1 General Revenue Fund | $19,616,513 | $19,616,512 |
| Total, as the request prints it | $19,616,513 | $19,616,512 |
Where it would land
The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.
| Strategy | Asked 2028 | Asked 2029 | Positions | Appropriated 2026 | Appropriated 2027 |
|---|---|---|---|---|---|
| 03-05-01 Exceptional Item Request | $19,616,513 | $19,616,512 | — | No strategy matched in the current budget | |
A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.
After 2029
| The agency's estimate | 2030 | 2031 | 2032 | Three years |
|---|---|---|---|---|
| All funds | $19,616,513 | $19,616,513 | $19,616,513 | $58,849,539 |
In the agency's words: These requests are for continuation or expansion of what is currently being done for this program.
The agency's justification
The University of Houston respectfully requests authorization for Capital Construction Assistance Project (CCAP) funding to construct a new Advanced Manufacturing Building. This 240,000 GSF facility will serve as the new front door to the Technology Bridge, strengthening the University’s position in fields such as biotechnology and biomanufacturing. It will provide incubator space, research suites, collaboration areas, and shared technical resources supporting commercialization. The project also replaces three outdated 1950s facilities requiring over $14 million in maintenance, with $4.7 million already spent in four years.
External and internal factors
This state of the art building will advance manufacturing, translational research, and collaboration with regional innovators, helping bridge the gap between discovery and real world application. CCAP support will expand the University’s research capacity, attract strategic partners, and enhance competitiveness in the rapidly growing life sciences community.
As marked in the request
- Has an information technology part: No
- Costs anticipated after the two budget years: Yes
- Involves contracts over $50,000: No