Flood Gage Network

Priority 5 · one of 11 items in the Water Development Board's request for 2028-29 · The item begins on page 163 of the request

This is a request, not an appropriation.

What is asked

20282029Two years
All funds$1,157,800$1,370,600$2,528,400
Of which general revenue and general revenue-dedicated $1,157,800$1,370,600$2,528,400
Positions (full-time equivalents) ——

How it would be financed

Method of financing, as the request prints it20282029
1 General Revenue Fund$1,157,800$1,370,600
Total, as the request prints it$1,157,800$1,370,600

Where it would land

The strategies this item would add to, numbered as the request numbers them, beside what each is appropriated in the current budget (2026-27 Act). One column is an appropriation and the other a request made on top of a base request not shown here, so the two are not subtracted.

Strategy Asked 2028Asked 2029Positions Appropriated 2026Appropriated 2027
01-01-02 Water Resources DataIn the current budget: A.1.2 WATER RESOURCES DATA $1,157,800$1,370,600— $4,789,362 $4,703,862

A strategy is matched by its name. Where none is matched, the strategy may be new, or may be in the current budget under a different name.

After 2029

The agency's estimate203020312032Three years
All funds$1,264,200$1,264,200$1,264,200$3,792,600

In the agency's words: This item will expand monitoring into smaller watersheds and areas prone to flash flooding, preserve critical gage operations affected by prospective federal funding cuts, and improve the reliability of flood data statewide, while requiring ongoing funding in future biennia to support continued deployment, upgrades, and maintenance of a robust network.

The agency's justification

The TWDB requests funding to expand and sustain a flood hardened streamflow gage network to improve statewide flood forecasting and warning capabilities . Flood-hardened gages collect critical streamflow data and are designed to remain operational during flood events, when data is most needed. Since 2016, the Texas Water Development Board (TWDB) has supported a network of 64 gages maintained by the U.S. Geological Survey; however, the July 2025 Hill Country floods, recent flooding events, and ongoing National Weather Service requests demonstrate the need for additional coverage. This funding will support the continued installation of new gages at a rate of 12–18 per biennium, the upgrade of at least 16 existing gages to flood hardened standards, and the ongoing maintenance of all new and upgraded stations, including six at-risk stations requiring state sponsorship. In the FY2028–FY2029 biennium, these investments will enable installation at up to 18 new locations and ensure 22 additional sites are upgraded and operational, affecting a total of 40 watershed locations. Initial guidance indicates at least 150 additional gages may ultimately be needed; accordingly, TWDB is undertaking a study to identify optimal locations and network scale. This item will expand monitoring into smaller watersheds and areas prone to flash flooding, preserve critical gage operations affected by prospective federal funding cuts, and improve the reliability of flood data statewide, while requiring ongoing funding in future biennia to support continued deployment, upgrades, and maintenance of a robust network.

External and internal factors

External Factors: Recent flooding events, including the July 2025 Hill Country floods, have demonstrated the need for improved flood monitoring and forecasting capabilities. The National Weather Service and emergency management partners continue to request additional streamflow data to support public safety. Potential reductions in federal funding also create a need for state support to maintain critical streamflow gage operations.

Internal Factors: To improve statewide flood forecasting and warning capabilities, additional resources are required for the flood-hardened streamflow gage network. Existing network 162 of 288 coverage is insufficient in some watersheds, particularly in areas vulnerable to flash flooding. Ongoing funding is required to install new gages, upgrade existing stations, and sustain long-term operations and maintenance.

As marked in the request